Information
back to projectsExpansion project on the Milcobel site in Kallo.
The tower building contains 3 stages in the production of milk powder: evaporators, spray drying tower, and filling. Each of these steps is characterized by a vertical set up. This is reflected in the choice of 3 vertical compartments and a technical compartment. In addition there is a completely new 'first processing', an extension of the car park and a new rainwater basin.
A massive concrete structure was chosen for the tower, consisting of precast hollow walls and cast in situ floor slabs.
STRUCTURAL ENGINEERING
Skald Engineering
company
skald
building site
Fabriekstraat 141
client
Milcobel
architect
DDRA architects
main contractor
Bolckmans, Alheembouw
floor surface
12.000 m²
building time
site start: January 2015
site end: July 2016