back to projectsSenior care facility (95 housing units) with short stay center, local service center and 30 service flats.
First a new building was constructed to expand the available surface area, then part of the existing centre was demolished and rebuilt with more respect for the adjacent historical monastery. Part of the existing structure within the monastery itself was also renewed.
company
evolv
building site
Wilsonstraat 28A, Sint-Katelijne-Waver
client
OCMW Sint-Katelijne-Waver
architect
CONIX RDBM Architects
main contractor
Antwerpse Bouwwerken
floor surface
9.610 m² (nieuwbouw 8.400 m², verbouwing 1.210 m²)
building time
phase 1:
site start: May 2017
site end: February 2019
phase 2:
site start: October 2020
site end: March 2022